THE DATA CENTER CAPITAL OF THE WORLD COULD HIT PAUSE • August 28, 2026
Loudoun County, Virginia is considering a temporary moratorium on new data center development.
On July 22, the Board of Supervisors voted 6-1 to have staff prepare options for a pause on new data center applications. The Board is expected to vote on September 15.
The scale here is what makes this different.
Media reports say Loudoun County is home to more than 250 data centers, with roughly 100 more already approved or in the development pipeline.
We are tracking even more.
Regarding Data Centers currently tracks 679 projects in Loudoun County: 204 operational, 144 in development, and 331 proposed.
That means 475+ projects are still somewhere in the pipeline.
That includes 61 AWS projects, 38 Equinix, 34 Digital Realty, 18 CyrusOne, 11 Vantage, 10 QTS, 10 Centersquare, 9 Microsoft, 9 Sabey, 8 NTT, and 8 EdgeCore, to name a few.
But there is a major legal question hanging over the September vote.
Loudoun County has said Virginia law does not give the Board authority to simply impose a blanket moratorium on all new data center applications. The question is how they can legally do it.
A pause limited to new rezonings or Special Exception applications would be very different from one that also reaches site plans, building permits, substations, or projects with existing approvals.
That is what we will be watching most closely on September 15: which applications are actually covered, and what mechanism Loudoun uses to slow the pipeline without running into Virginia law.
The moratorium is also not the only thing being discussed.
Supervisors are pushing to end Loudoun’s 2025 data center grandfathering resolution, which could send more than 20 pending applications back through the county’s newer Special Exception process.
This is the center of Northern Virginia’s data center market, with hundreds of projects already operating and hundreds more proposed or under development.
A meaningful pause here would hit the data center pipeline at a scale we have not really seen before.
We don’t believe the market has fully priced that in.
All eyes on September 15.
A MORATORIUM ON MORATORIUMS · AUGUST 28, 2026
Nearly two-thirds of communities acting against data centers have no proposed or operational data centers.
DATA CENTER MORATORIUMS · Aug 28, 2026
PASSED (3)
Ormond Beach, FL — none tracked
Escambia County, FL — none tracked
Elkhart, IN — none tracked
DISCUSSING (6)
Lancaster County, NE — 6 projects
Lordstown, OH — none tracked
Indiantown, FL — none tracked
Foley, AL — none tracked
San Antonio, TX — none tracked
Kenosha, WI — none tracked
6 data center projects tracked across 1 of these 9 communities
3 operational · 3 proposed
@acemoney21 Enacted means there’s an active data center moratorium. Proposed means one is being discussed, not yet enacted.
Going to keep refining these posts until they are easily digestible. There’s also different time periods the moratoriums are in place.
DATA CENTER MORATORIUMS · Aug 26, 2026
ENACTED (12)
Orangetown, NY · Missoula County, MT · Lowndes County, GA · Tulare County, CA · Harlingen, TX · Carlton County, MN · Emmet County, IA · Calaveras County, CA · Gibraltar, MI · Madison County, AR · Garfield, MI · Kings Mountain, NC
PROPOSED (8)
Lubbock, TX · Lincoln County, SD · Oshkosh, WI · Savannah, GA · Venice, FL · Helena, AL · Winnebago County, WI · Appleton, WI
DATA CENTER DENIED · Pinal County, AZ · Aug 26, 2026
Pinal County rejected Vermaland’s massive La Osa Energy Center in a 4-1 vote.
The proposed 3,385-acre campus included:
• Up to 11 data center buildings
• ~400,000 sq. ft. per building
• Up to 1 GW of power demand
• 500 MW of planned on-site natural gas generation
The project had already been scaled down from an earlier proposal for as many as 59 data center buildings and 3 GW of power demand.
CONSTRUCTION START SIGNAL · Kendall County, IL · Aug 25, 2026
CyrusOne submitted an obstruction evaluation for a 160-foot crane at its CHI 11A - Yorkville data center campus in Kendall County, Illinois, with case status Evaluating as of August 25, 2026.
Crane obstruction filings typically precede crane deployment, making them an early signal that major construction activity is approaching.
11 tracked data center projects in Kendall County.
DATA CENTER REJECTED · AUGUST 25, 2026
Coweta County, GA, unanimously denied Project Oak, a proposed 255-acre data center campus with five buildings, more than 895,000 square feet of space, and 280 MW of planned power capacity.
According to the Development of Regional Impact report, Project Oak would use 28,000 gallons of water per day.
Protect Coweta County, a nonprofit organization, is also opposed to Project Sail, Project Peach, Bridgeport, and Project Pegasus. They are actively recruiting citizens for petitioning signatures.
DATA CENTER MORATORIUM · Aug 26, 2026: Durham County, NC passed a nine-month data center moratorium.
We currently track 4 projects in the county:
3 operational
1 in development
1K Followers 2K FollowingAbogado especialista Derecho administrativo y Contencioso-administrativo. Perfil PERSONAL y de OPINIÓN. No Financial Advice. 📞 681.18.87.56 | ✉ [email protected]
141K Followers 836 FollowingVantor is forging the new frontier of spatial intelligence to unlock a more automated, interoperable world. Delivering total clarity from space to ground.
16K Followers 2K FollowingThe leader in data center events. Driving innovation in infrastructure, technology & sustainability. Connect with us at #DataCenterWorld 🌐
35K Followers 1K FollowingWe are dedicated to being the go-to resource for all things data center, providing the information and insights needed to navigate and thrive in this industry.
5K Followers 295 FollowingActionable data on companies that matter to you. We analyze billions of data points every day to provide accurate, granular insights.
[email protected]
4.4M Followers 159 FollowingValues are most enduring thing leaders create. Engineering pioneer, proud grandfather, philanthropist, Christian, farm boy at heart.
2K Followers 240 FollowingRigaku Companies are world leaders in XRD, XRF, SAXS, Raman, semiconductor metrology, protein and small molecule crystallography.
4K Followers 190 Followinghttps://t.co/qM3M70IFyM
https://t.co/uo4gH9eyE2
I draw lines on charts that I think are useful. Shared for educational purposes. Not advice.
77K Followers 2K FollowingFounder @3F_Research | PM $RAA | $FCTE | Formerly with Ned Davis Research | Recovering Attorney (step 4) - Not investment advice
29K Followers 811 FollowingHead of commodities macro, AI PhD, sarcasm & counterstrike. Up +3000x in 6.5 yrs of investing. Posts are speculations - not financial advice
489K Followers 287 FollowingNews on the global tech industry
Watch Bloomberg Tech weekdays on Bloomberg TV at 11 am ET
Podcast: https://t.co/8kX0blvfVk
Newsletter: https://t.co/CRIkTrOEKi
860K Followers 143 FollowingChief Market Strategist @ Creative Planning
Investor | Writer | Reader | Thinker
Trying to become a little wiser every day.
424K Followers 1K FollowingWe are an independent investing research and financial media company. Not Investment Advice. Access our research at https://t.co/7g2FfaekGA.